Breightmet Health Centre

> BOLTON

PRINCIPAL CONTRACTOR: Eric Wright Construction Ltd CLIENT: NHS Primary Care Trust VALUE: £865,000.00
WORKS PACKAGE: Internal Partitions, Suspended Ceilings& Decorative Bulkheads

The new health facility was constructed to the rear of the then existing health centre. Once the new facility was completed the existing centre was demolished and a new car park formed on this area.

Due to the performance and proactive approach taken on CLM’s previous PCT projects with Eric Wright Construction, CLM were again successful in the tender of the internal partitions and suspended ceilings package.

The works were completed over a period of 32 weeks on this 9,000m2 project using British Gypsum plasterboard, metal stud partitions and a variety of tile and grid systems. Specialist hygiene tiles and perforated metal pan tiles with silhouette grids were also used.

The building is constructed in steel frame with precast concrete driven piles, reinforced concrete foundations and precast ground floor units achieving ‘Excellent’ standard in the NHS Environmental Assessment Tool.

In recognition of the remarkable achievements this project has been awarded with Best Health care Building at the 2009 LABC Building Excellence Awards.